My budget that I was given was $700 dollars and the supplies I will need are listed right here:
-
4 bags of cement which will be approximately $16.
-
I will need 360 12x12in pavers in which I already price checked with Home Depot and it will cost $150.
-
I will also need 20 bags of leveling sand which is an additional $50 dollars.
-
The BBQ was donated and I have all the tools I need to complete this project.
-
I will recruit some helpers and I have a goal of completion in 1 month time.
The total amount that I will need is $216 dollars which will leave $484 which will help go towards phase two which is new playground equipment.
Timeline:
I’ve started the project June 12, 2016 and the time I have scheduled to be complete is July 12, 2016.
-
Week one in this project I will have the bench seat installed.
-
Week two and three will be the construction of the stage, this will take me more time to lay the leveling sand making sure the sand is level and placing the pavers. Cutting the pavers with a tile saw will take a little bit of time as well.
Week 4 I will have dug the footing for the BBQ and have it installed finishing by July 10, 2016.
Presentation
Here Below is my timeline and the budget break down of what I was able to accomplish. Towards the bottom of the page is a letter written to me. Jolene Lee the president of the park committee, explains in detail of the work and progress that was done. If you have any questions about the Garden Park presentation please feel free to contact me through my e-mail.